Uttar Pradesh

Kanpur Metro, UPMRC, Kanpur News Today, Kanpur News Hindi, Kanpur | Metro laid U-girder in CSA to Barra-8 section: First girder weighing 160 metric tons was laid at Companybagh intersection; 184 more will be kept – Kanpur News


Kanpur Metro laid the first U-girder on the second corridor.

Kanpur Metro has now accelerated the construction work on CSA to Barra-8 section. Erection work of U-girder was started on Tuesday. In the morning, U-girder was first placed on pillar number 13 and 14 near Companybagh intersection. About 184 U-Gards in this section

,

U-girder weighing 160 metric tons was placed The work of placing the U-girder, approximately 28 meters long and weighing 160 metric tons, was started in the presence of senior officials of Kanpur Metro and the executing agency. These are cast in the casting yard and then placed at designated places in the corridor with the help of cranes.

A girder weighing 160 metric tons was placed at Companybagh intersection.

5 metro stations will be built Under the second corridor (CSA to Barra-8), about 4.5 km long elevated section is being constructed from Agricultural University to Corridor-2 depot ramp and from double culvert ramp to Barra-8. A total of 5 stations in this section are Agricultural University, Vijay Nagar Square, Shastri Chowk, Barra-7 and Barra-8.

Foundation of metro corridor laid Piling for the Agricultural University Barra-8 elevated section, which can also be called the foundation of the metro corridor. Its work started on 2 July 2024. The casting work of U-girder started at Naubasta Casting Yard on 3 July 2024. On September 9, 2024, the first pier cap was placed near the Companybagh intersection.

Metro will run till Central Station in January 2025 UPMRC Managing Director Sushil Kumar, while congratulating the team of metro engineers on this achievement, said that along with the balance section of Corridor-1 of Kanpur Metro, the civil construction work of Corridor-2 is also progressing rapidly. .

Soon a trial run of the train will be done beyond Motijheel till Kanpur Central, after which the metro will start running till Kanpur Central by January 2025.



Source link