IIT Metro station is ready, the first station made in saffron color, the work of Kalyanupar station is also almost complete, Kanpur Metro, UPMRC, IIT Kanpur, Kalyanpur station, Kanpur | IIT Metro station is ready, the first station made in saffron color, the work of Kalyanupar station is also almost complete


  • Hindi News
  • Local
  • Uttar pradesh
  • Kanpur
  • IIT Metro Station Is Ready, The First Station Made In Saffron Color, The Work Of Kalyanupar Station Is Also Almost Complete, Kanpur Metro, UPMRC, IIT Kanpur, Kalyanpur Station, Kanpur

Kanpur8 minutes ago

  • copy link

Kanpur Metro is moving towards becoming the shortest trial run metro in the country.

Kanpur Metro has started taking its form. The construction of the track is almost 90 percent complete. Metro stations have also started getting ready. Kanpur’s first metro station is almost ready. It looks very beautiful in the first pictures released of IIT Metro station. The metro station has been painted in white and orange colours.

Such is the view of the metro station from inside.

Such is the view of the metro station from inside.

fastest in the country
Kanpur Metro is moving towards becoming the shortest trial run metro in the country. Pune Metro covers 5 km in 30 months. Trial run was done at a distance. Whereas Lucknow Metro covered 6 km in 32 months. Trial run record was set at the distance. Kanpur Metro is making full preparations to break it. 9 kms in 24 months. Trial run will be done. It is also different because the distance will be more and the time will be shortest. Hardly anyone will be able to break this record in the country. The trial run is targeted in November-2021.

After checking and taking tickets on the first floor, the metro will be available on the second floor.

After checking and taking tickets on the first floor, the metro will be available on the second floor.

These stations are in Priority Corridor
IIT, Kalyanpur, Housing Development, CSJM University, Geeta Nagar Crossing, Gurudev Palace, Rawatpur, Medical College, Motijheel.

The lobby and ticket counter were also ready.

The lobby and ticket counter were also ready.

Kanpur Metro in figures
9 Metro stations were placed in the Priority Corridor.
-9 kms. Track construction almost complete.
Trial run proposed in November-2021.
117 total coaches will come in Kanpur Metro.
There will be one train of 3 coaches.
-39 trains will run on the metro track.
-29 train will run between IIT to Naubasta.
-8 trains will run between CSA to Barra-8.

The work of Gurudev Metro station is also going to be completed soon.

The work of Gurudev Metro station is also going to be completed soon.